FACILITIES
MANAGEMENT OFFICE PROJECT COST MULTI-PURPOSE MACHINE GUN (RETS) RANGE $1,253,687 VENTILATING AND AIR CONDITIONING SYSTEMS, BUILDING 2-1;
AND ALTERATIONS TO AIR AMMUNITION SURVEILLANCE FACILITY $306,863 EQUIPMENT CLEANING MAINTENANCE FACILITY, MISCELLANEOUS PROJECTS $1,624,368 PROCUREMENT ACTIONS $1,315,773 TOTAL ALL PROJECTS $5,479,212FEDERAL FUNDS $4,874,682 STATE FUNDS $604,530 |